The Shah Deniz consortium today announced commencement of commercial gas deliveries to Europe from the Shah Deniz gas field in the Caspian Sea offshore Azerbaijan via the newly-completed Southern Gas Corridor (SGC) pipeline system. The start of gas deliveries through the final section of the SGC – the Trans Adriatic Pipeline (TAP) – marks the full integration of the entire SGC gas value chain, stretching 3,500 kilometres from Azerbaijan to Europe.
Deliveries through this final stage of the system follow safe and reliable gas deliveries to regional markets from the Shah Deniz field via the first two sections of SGC – the South Caucasus Pipeline expansion (SCPx) and Trans-Anatolian Pipeline (TANAP) – that started mid-2018.
The Shah Deniz field is the starting point of SGC, which has been built to deliver Caspian energy resources directly to European markets for the first time. The field is expected to supply 16 billion cubic meters of gas to markets in the region and Europe via SGC.
Rovnag Abdullayev, President of SOCAR, said: "On this historic day, we express our deep gratitude to the partner companies, specialists and all our colleagues, who participated in TAP, Shah Deniz 2 and the Southern Gas Corridor projects, contributing to the first delivery of Azerbaijani gas to the European market. We thank all financial institutions that supported this project and the residents of the communities where our pipelines pass. As a shareholder in all Southern Gas Corridor segments, SOCAR is proud of the successful completion of this historic mission. On behalf of Azerbaijani oil workers, I congratulate both the people of the European Union and the people of Azerbaijan. We express our utmost gratitude and extend our congratulations to Mr. Ilham Aliyev, the President of the Republic of Azerbaijan, the author and the leader of this initiative!
"Seven years ago, we made the final investment decision together with our partners. We embarked on this journey by signing 25-year gas sales agreements with European gas distribution companies. The construction of three interconnected gas pipelines across continents with a total length of 3,500-kilometres was a highly complex endeavour. Back then, some were sceptical about this project. Now the mission is accomplished – Azerbaijan’s natural gas has arrived in Europe. Coming from a new source through an alternative route, it will contribute to European energy security. We anticipate a growing demand for additional gas volumes on the European market due to the constant local production decline. Our gas will fill this gap for decades to come, and the importance of cooperation between the Old Continent and Azerbaijan will increase."
Gary Jones, Regional President for Azerbaijan, Georgia and Turkey for bp, the operator of Shah Deniz, said: "The start of gas deliveries to Europe from Azerbaijan is the culmination of years of work by many thousands of people from all the countries involved – the workforce, communities, companies, the government of Azerbaijan and other regional and international governments, and SOCAR and our partners. This is a truly world-class project in all respects.
"We are very proud of what we have achieved together. Notwithstanding the complexity of all aspects of the project – engineering, technical, geographical and geopolitical – it has been delivered safely, on schedule and under budget. This is an historic milestone, with Azerbaijan and Europe now connected with a direct, safe and reliable energy link, that again demonstrates that together we can deliver the most complex mega-scale projects successfully."
Tamam Bayatly in bp's Press Office in Azerbaijan.
Telephone: (+994 12) 599 45 57
In order to utilize the ‘safe harbor’ provisions of the United States Private Securities Litigation Reform Act of 1995 (the ‘PSLRA’), bp is providing the following cautionary statement. This press release contains certain forward-looking statements – that is, statements related to future, not past events and circumstances – which may relate to one or more of the financial condition, results of operations and businesses of bp and certain of the plans and objectives of bp with respect to these items. These statements are generally, but not always, identified by the use of words such as ‘will’, ‘expects’, ‘is expected to’, ‘aims’, ‘should’, ‘may’, ‘objective’, ‘is likely to’, ‘intends’, ‘believes’, ‘anticipates’, ‘plans’, ‘we see’ or similar expressions. Actual results may differ from those expressed in such statements, depending on a variety of factors including the risk factors set forth in our most recent Annual Report and Form 20-F under “Risk factors” and in any of our more recent public reports.