bp as operator of the Azeri-Chirag-Deepwater Gunashli (ACG) field development project announces that today the Azeri Central East (ACE) platform topsides unit sailed away from the Bayil fabrication yard where it was built. Prior to its sail away the topsides unit was mostly commissioned and operationally tested onshore to minimise activities required for offshore installation and start-up.
On 4 April, the President of Azerbaijan Ilham Aliyev visited the topsides fabrication yard and toured the almost completed topsides unit before it had sailed away to its permanent location. Since then, the team have successfully completed the key commissioning activities planned to be performed onshore. These activities mainly included the successful completion of the rig access period, the integrated assurance test and the blowdown safety testing.
Following these completions, the topsides unit was safely jacked-up and lowered onto the load-out frame in preparation for skidding onto the transportation barge.
On 30 May, the transportation barge STB-1 arrived at the Bibi-Heybat yard and preparations for load out activities commenced. On 2 July, the topsides unit was transferred onto the STB-1 barge, sea-fastened and prepared for sail away to the ACG field.
The topsides transportation, float-over and installation activities have been carefully planned and are expected to take around four days to complete. The unit will be installed on top of the ACE platform jacket which has been at its offshore location since March installed in a water depth of 137 metres.
“Today we sailed away the final section of the ACE platform which we believe is an amazing feat of innovative engineering with its state-of-the-art design that will make it possible to extensively use system and process automations and digital innovations. This platform will be controlled remotely from the Sangachal terminal and this is the first time in our experience in the Caspian that we will control an offshore platform from onshore.
As operator we are extremely pleased to have completed all onshore construction and commissioning activities of such a complex project safely. I would like to say a huge thank you to all people involved in the construction and commissioning works. My special thanks are to our fabrication contractors, construction, commissioning, operations, safety and engineering teams and all the workforce for their excellent performance and delivery.
We expect the topsides unit to be safely installed onto the jacket over the next week. We will then need a few months to complete offshore hook up and commissioning works to allow us to commence drilling the first platform production well and deliver ACE first oil in early 2024.”
Notes to editors
Tamam Bayatly at bp’s press office in Baku.
Telephone: (+994 12) 525 58 95