1. Home
  2. News
  3. Press releases
  4. bp announces a new ACE milestone

bp announces a new ACE milestone

Release date:
28 July 2022

bp as operator of the Azeri-Chirag-Deepwater Gunashli (ACG) field announces that the Azeri Central East (ACE) project, which is the next phase of the ACG development, has achieved a major milestone by safely and efficiently transporting, jacking and skidding two drilling modules onto the ACE topsides deck currently under construction.  


The two drilling modules - the Modular Drilling Support Module (MDSM) and the Drilling Equipment Set (DES) were fabricated on the ground separately from the topsides deck before commencing the “Jack and Skid” operation. The MDSM module weighs 2,350 tonnes measuring 43m long, 20m wide and 20m high, whilst the DES module weighs 2,400 tonnes and is 32m long, 22m wide and 80m high. They were built at the fabrication yard in Bibi-Heybat.

 

Neal Phillips, project general manager for the ACE project, said

 

"This was a complex operation and a first for bp in the Caspian. During the operation self-propelled modular trailers were installed underneath the modules to transport them to the main jacking position adjacent to the topsides deck. The modules were then jacked up by incrementally installing steel cassettes to reach the final height of around 27 metres. Hydraulic rams were used to skid the modules onto the topsides deck before set-down at their final locations. We are proud to have achieved this unique milestone safely and ahead of schedule. It allowed us to commence commissioning at grade ahead of the integration of the module."

 

Cathal Kelly, bp’s vice president, projects, for the Azerbaijan, Georgia, Türkiye region, Egypt and Oman:

 

"The lifting and successful integration of the two drilling facilities on the ACE topsides deck marks a major milestone towards achieving the overall completion of the ACE project. Completion of this activity is the result of nearly four years of engineering and fabrication work in close collaboration with a group of ACE project contractors including Azfen, NOV, SOCAR-KBR and Mammoet. I would like to thank all people who have contributed to this remarkable achievement.”

 

Bakhtiyar Aslanbayli, bp’s vice president for the Caspian region, Communications and External Affairs, said:

 

"We are on track to bring our next ACG platform – ACE, online in support of our efforts to effectively manage production from ACG. In 2017, we extended the ACG contract till mid-century and as Azerbaijan’s long term energy partner, we have a commitment to continue operating the ACG field safely, efficiently and reliably.

 

We have been in Azerbaijan for 30 years and at least over the next three decades we will be here working together with the government, SOCAR and our co-venturers to unlock the long-term development potential of ACG through new investments, new technologies and new joint efforts to maximise recovery."

 

The overall ACE construction and commissioning activities are currently at peak with around 75% of the project completed and with about 5,000 people across Baku, Europe and the UK, with the majority of them being Azerbaijani nationals.

 

Notes to editors

 

  • ACG participating interests are: bp (30.37%), SOCAR (25.0%), MOL (9.57%), INPEX (9.31%), Equinor (7.27%), ExxonMobil (6.79%), TPAO (5.73%), ITOCHU (3.65%), ONGCVidesh (2.31%).
  • ACG has continued safe and reliable operations during 2022.
  • Total oil production from ACG since start has reached around 4.1 billion barrels.
  • Total production for the first quarter was on average about 434,000 barrels per day (b/d) (about 39 million barrels or 5 million tonnes in total)
  • ACG delivered an average of around 12 million cubic metres per day of associated gas to the state of Azerbaijan (1 billion cubic metres in total) in the first quarter. The remainder of the associated gas produced was re-injected for reservoir pressure maintenance.
  • At the end of the quarter, 137 oil wells were producing, while 37 were used for water and eight for gas injection.

 

Further information

 

Tamam Bayatly at bp’s press office in Baku. 

Telephone: (+994 12) 525 58 95